South Ferriby Flood Defences - Construction

Traffic Management Information

A lane closure to the eastbound side of the A1077 in the vicinity of the Sluice & Lock on the Ancolme scheduled for 14 weeks commencing 11th January 2021 was removed early on 26th March 2021

A lane closure to the A1077 in the vicinity of the CEMEX Gate to install the new Vehicle Restraint System is scheduled for 3 weeks commencing 4th May 2021

Week Beginning: 12th April 2021

No. of people on site (approx): 19

Social Media links:

Forecast lorry movements per day (approx): 30

South Ferriby Residents Group

Traffic Movement

  • All Clear 0% 0%
  • Some Lorries 40% 40%
  • Lots of Lorries 0% 0%
  • Temporary Traffic Lights 0% 0%
  • Road Closures 0% 0%

Please drive carefully when you see contractors working close to the side of the road

Outline of work to be undertaken this week

Continue reinstatement works east of East Drain Bridge (weather dependent)

Flood Defence around Hope & Anchor – Continue reinstatement kerbing and painting

Continue works at Fulseas Drain for installation of telemetry and associated MEICA install plus installation of stone track

Continue works to West Embankment commence installation of a drainage pipe from dry side drainage ditch to the existing wet side drainage infrastucture

Continue earth embankment installation works either side of CEMEX Gate (Weather dependent)

Continue drainage works and extension of CEMEX embankment at the southern end of CEMEX

Additional works around Sluice to reinstall the eastern sluice gate tidal door if not completed w/c 5/4/2021 (Wind dependent)

Useful contact numbers:

Contractor – JBA Bentley – Tom Sherwood – 07970 532 127

Environment Agency       – Contact Centre – 03708 506 506

Parish Council                 – Cllr Sara Haddon – 07808 958957
– Cllr Roy Holloway – 01652 635 417

Week Beginning: 19th April 2021

No. of people on site (approx): 19

Social Media links:

Forecast lorry movements per day (approx): 30

South Ferriby Residents Group

Traffic Movement

  • All Clear 0% 0%
  • Some Lorries 40% 40%
  • Lots of Lorries 0% 0%
  • Temporary Traffic Lights 0% 0%
  • Road Closures 0% 0%

Please drive carefully when you see contractors working close to the side of the road

Outline of work to be undertaken this week

Continue reinstatement works east of East Drain Bridge (weather dependent)

Flood Defence around Hope & Anchor – Continue reinstatement surfacing to car park and white lining

Continue works at Fulseas Drain for installation of telemetry kiosk and associated MEICA install – NPG power connection plus commence removing surplus materials and temporary compound

Continue works to West Embankment continue installation of a drainage pipe from dry side drainage ditch to the existing wet side drainage infrastucture

Continue earth embankment installation works either side of CEMEX Gate (Weather dependent)

Continue drainage works and extension of CEMEX embankment at the southern end of CEMEX

Installation and testing of demountable barriers on top of the lock structure

Useful contact numbers:

Contractor – JBA Bentley – Tom Sherwood – 07970 532 127

Environment Agency       – Contact Centre – 03708 506 506

Parish Council                 – Cllr Sara Haddon – 07808 958957
– Cllr Roy Holloway – 01652 635 417

Week Beginning: 26th April 2021

No. of people on site (approx): 19

Social Media links:

Forecast lorry movements per day (approx): 30

South Ferriby Residents Group

Traffic Movement

  • All Clear 0% 0%
  • Some Lorries 40% 40%
  • Lots of Lorries 0% 0%
  • Temporary Traffic Lights 0% 0%
  • Road Closures 0% 0%

Please drive carefully when you see contractors working close to the side of the road

Outline of work to be undertaken this week

Continue reinstatement works east of East Drain Bridge (weather dependent)

Flood Defence around Hope & Anchor – Final reinstatement and hand back

Continue works at Fulseas Drain for commissioning of telemetry MEICA installation plus continue removing surplus materials and temporary compound

Continue works to West Embankment complete installation of a drainage pipe from dry side drainage ditch to the existing wet side drainage infrastucture and reinstatement of embankment

Continue earth embankment finishing works either side of CEMEX Gate (Weather dependent)

Continue drainage works and extension of CEMEX embankment at the southern end of CEMEX

Useful contact numbers:

Contractor – JBA Bentley – Tom Sherwood – 07970 532 127

Environment Agency       – Contact Centre – 03708 506 506

Parish Council                 – Cllr Sara Haddon – 07808 958957
– Cllr Roy Holloway – 01652 635 417

Week Beginning: 3rd May 2021

No. of people on site (approx): 19

Social Media links:

Forecast lorry movements per day (approx): 30

South Ferriby Residents Group

Traffic Movement

  • All Clear 0% 0%
  • Some Lorries 40% 40%
  • Lots of Lorries 0% 0%
  • Temporary Traffic Lights 40% 40%
  • Road Closures 0% 0%

Please drive carefully when you see contractors working close to the side of the road

Outline of work to be undertaken this week

Continue reinstatement works east of East Drain Bridge (weather dependent)

Completion works at Fulseas Drain removing temporary compound and completion of fencing

Continue works to West Embankment complete reinstatement of embankment

Continue earth embankment finishing works either side of CEMEX Gate (Weather dependent)

Continue drainage works and extension of CEMEX embankment at the southern end of CEMEX

Installation of traffic lights at CEMEX Gate area and commence installation of Vehicle Restraint System (VRS) to verges

Useful contact numbers:

Contractor – JBA Bentley – Tom Sherwood – 07970 532 127

Environment Agency       – Contact Centre – 03708 506 506

Parish Council                 – Cllr Sara Haddon – 07808 958957
– Cllr Roy Holloway – 01652 635 417

Planning changes to Flood Defences – Improved traffic Restrictions – EA Engagement Video

 


Some parts of South Ferriby are at risk of flooding and with the advent of climate change and a greater focus on environmental issues the Parish Council has prepared a flood contingency plan for those living on lower ground.

Flood Risk Contact List and Important Numbers

For more information about the flood plan contact Sara Haddon or Roy Hollaway via the Clerk on 07393 21 30 30 or by email

 

Emergency Telephone Numbers

South Ferriby Flood Wardens:

Roy Holloway 07899 906433
Dave Mouncey  07799 151255

North Lincolnshire Council  01724 297000
Environment Agency Floodline 0845 988 1188
Anglian Water 08457 919155

Contact the Clerk

Holly Hanson
Appledore
26 Main Street
Horkstow
Barton-upon-Humber
DN18 6BG

T: 07393 21 30 30