Flood Defences

South Ferriby Flood Defences – Construction

Planning changes to Flood Defences – Improved traffic Restrictions – EA Engagement Video

Traffic Management Information

A lane closure to the eastbound side of the A1077 in the vicinity of the Sluice & Lock on the Ancolme has been scheduled for 14 weeks commencing 11th January 2021 to raise and strengthen flood defences to the North of the road

A Full Road Closure has been scheduled for the February 2021 Half Term starting Saturday 13th February for up to 7 days and programmed to be complete by Friday 19th February 2021.

There will still be some periods where there is one-way traffic either side of the road closure to install safety fencing to the verge of the road either side of CEMEX gate.

Week Beginning: 18th January 2021

No. of people on site (approx): 17

Social Media links:

Forecast lorry movements per day (approx): 5

South Ferriby Residents Group

Traffic Movement

  • All Clear 0% 0%
  • Some Lorries 40% 40%
  • Lots of Lorries 0% 0%
  • Temporary Traffic Lights 40% 40%
  • Road Closures 0% 0%

Please drive carefully when you see contractors working close to the side of the road

Outline of work to be undertaken this week

Continue reinstatement works east of East Drain bridge (weather dependent)

Continue CEMEX Gate (South side off road) – Tidy area and prepare crane pads remove any temporary works

Works to Sluice and Lock – Commence works to strengthen northern sluice parapet

Works to Sluice and Lock – Commence works to provide level foundations adjacent to lock for installation of demountable barriers to lock pier

Works to Sluice and Lock – Works to raise existing concrete wall to west of sluice / fix reinforcement and shutters to wall and concrete to same

Useful contact numbers:

Contractor – JBA Bentley – Tom Sherwood – 07870 391 668

Environment Agency – Contact Centre – 03708 506 506

Parish Council           – Cllr Sara Haddon – 07808 958957
                                  – Cllr Roy Holloway – 01652 635 417

Week Beginning: 25th January 2021

No. of people on site (approx): 17

Social Media links:

Forecast lorry movements per day (approx): 5

South Ferriby Residents Group

Traffic Movement

  • All Clear 0% 0%
  • Some Lorries 40% 40%
  • Lots of Lorries 0% 0%
  • Temporary Traffic Lights 40% 40%
  • Road Closures 0% 0%

Please drive carefully when you see contractors working close to the side of the road

Outline of work to be undertaken this week

Continue reinstatement works east of East Drain bridge and East Drain bridge copings (weather dependent)

Continue CEMEX Gate (South side off road) – minor works / rubbing up / winch plinths / preparation for road closure

Works to Sluice and Lock – Continue works to strengthen northern sluice parapet

Works to Sluice and Lock – Continue works to east of lock construction of flood defences

Works to Sluice and Lock – Works to raise existing concrete wall to west of sluice / fix reinforcement and shutters to wall and concrete to same

Useful contact numbers:

Contractor – JBA Bentley – Tom Sherwood – 07970 532 127

Environment Agency       – Contact Centre – 03708 506 506

Parish Council                 – Cllr Sara Haddon – 07808 958957
– Cllr Roy Holloway – 01652 635 417

Week Beginning: 1st February 2021

No. of people on site (approx): 17

Social Media links:

Forecast lorry movements per day (approx): 5

South Ferriby Residents Group

Traffic Movement

  • All Clear 0% 0%
  • Some Lorries 40% 40%
  • Lots of Lorries 0% 0%
  • Temporary Traffic Lights 40% 40%
  • Road Closures 0% 0%

Please drive carefully when you see contractors working close to the side of the road

Outline of work to be undertaken this week

Continue reinstatement works east of East Drain bridge and East Drain bridge copings (weather dependent)

Continue CEMEX Gate (South side off road) – minor works / rubbing up / winch plinths / preparation for road closure

Works to Sluice and Lock – Complete works to strengthen northern sluice parapet

Works to Sluice and Lock – Continue works to east of lock construction of flood defences

Works to Sluice and Lock – Works to raise existing concrete wall to west of sluice / fix reinforcement and shutters to wall and concrete to same

Useful contact numbers:

Contractor – JBA Bentley – Tom Sherwood – 07970 532 127

Environment Agency       – Contact Centre – 03708 506 506

Parish Council                 – Cllr Sara Haddon – 07808 958957
– Cllr Roy Holloway – 01652 635 417

Week Beginning: 8th February 2021

No. of people on site (approx): 17

Social Media links:

Forecast lorry movements per day (approx): 5

South Ferriby Residents Group

Traffic Movement

  • All Clear 0% 0%
  • Some Lorries 40% 40%
  • Lots of Lorries 0% 0%
  • Temporary Traffic Lights 40% 40%
  • Road Closures 0% 0%

Please drive carefully when you see contractors working close to the side of the road

Outline of work to be undertaken this week

Continue reinstatement works east of East Drain bridge and East Drain bridge copings (weather dependent)

Continue CEMEX Gate (South side off road) – minor works / rubbing up / winch plinths / preparation for road closure

A Full Road Closure to Sluice road at CEMEX Gate commences Saturday 13th February for up to 7 days.

Works to Sluice and Lock – Remove scaffolding from sluice parapet

Works to Sluice and Lock – Continue works to east of lock construction of flood defences

Works to Sluice and Lock – make good all area to west of Sluice

Useful contact numbers:

Contractor – JBA Bentley – Tom Sherwood – 07970 532 127

Environment Agency       – Contact Centre – 03708 506 506

Parish Council                 – Cllr Sara Haddon – 07808 958957
– Cllr Roy Holloway – 01652 635 417

Week Beginning: 15th February 2021

No. of people on site (approx): 19

Social Media links:

Forecast lorry movements per day (approx): 5

South Ferriby Residents Group

Traffic Movement

  • All Clear 0% 0%
  • Some Lorries 40% 40%
  • Lots of Lorries 0% 0%
  • Temporary Traffic Lights 40% 40%
  • Road Closures 40% 40%

Please drive carefully when you see contractors working close to the side of the road

Outline of work to be undertaken this week

Continue reinstatement works east of East Drain bridge and East Drain bridge copings (weather dependent)

Continue CEMEX Gate – A Full Road Closure to Sluice road at CEMEX Gate commences Saturday 13th February for up to 7 days for installation of the flood gate running rail, flood gate and associated resurfacing works

Works to Sluice and Lock – Continue works to east of lock construction of flood defences

Works to Sluice and Lock – works to raise existing concrete wall to west of sluice / fix reinforcement and shutters to wall

Useful contact numbers:

Contractor – JBA Bentley – Tom Sherwood – 07970 532 127

Environment Agency       – Contact Centre – 03708 506 506

Parish Council                 – Cllr Sara Haddon – 07808 958957
– Cllr Roy Holloway – 01652 635 417

South Ferriby Flood Defences – Additional Information

Some parts of South Ferriby are at risk of flooding and with the advent of climate change and a greater focus on environmental issues the Parish Council has prepared a flood contingency plan for those living on lower ground.

Flood Risk Contact List and Important Numbers

Some parts of South Ferriby are at risk of flooding and with the advent of climate change and a greater focus on environmental issues the Parish Council has prepared a flood contingency plan for those living on lower ground.

For more information about the flood plan contact Sara Haddon or Roy Hollaway via the Clerk on 07393 21 30 30 or by email May open an email client if one is installed.

Emergency Numbers

South Ferriby Flood Wardens

Roy Holloway 07899 906 433
Dave Mouncey 07799 151 255

Miscellaneous

North Lincolnshire Council 01724 297 000
Environment Agency Floodline 0845 988 1188
Anglian Water 08457 919 155

Clerk

Ann Boulton
21 Hallam Close
Barrow upon Humber
DN19 7FD

Telephone

07592 66 60 58