South Ferriby Flood Defences - Construction

Traffic Management Information

Temporary traffic lights will be in use near the bowling green on Sluice Road to control traffic during the removal of the concrete blocks at the side of the road during wc 28th October and wc 4th November.

The temporary traffic lights will only be in operation during off peak hours between 9.30am and 3.30pm.

The Planning Application envisaged up to 30 weeks of road closures.

We are now advised by the Contractor that the actual time the road is closed will, be significantly less than this.

JBA Bentley are currently working on their work programme and need to satisfy the conditions attached to the planning application.

We can confirm that there will be no road closures during 2019.

Future Works Programme

July 2019 to October 2019 – East Embankment (East Drain to Lowish Farm)

April 2020 – June 2020 – West Embankment (Section around CEMEX football pitch)

April 2020 to September 2020 CEMEX Embankment

September 2019 to June 2020 – Hard defences from Sluice to East Drain tie in with the embankment

Andrew Percy visited the South Ferriby Flood Defence works on Friday 12th July to check on progress for the project.  Please click here for the visit update.

Week Beginning: 21st October 2019

No. of people on site (approx): 15

Social Media links:

Forecast lorry movements per day (approx): 150

South Ferriby Residents Group

Traffic Movement

  • All Clear 0% 0%
  • Some Lorries 0% 0%
  • Lots of Lorries 40% 40%
  • Temporary Traffic Lights 0% 0%
  • Road Closures 0% 0%

Please drive carefully when you see contractors working close to the side of the road

Outline of work to be undertaken this week

Depending on the weather we will be completing the east embankment in the area just west of Fulseas Drain.

We will be transporting the remaining clay required to complete the East Embankment along Sluice Road from the CEMEX plant.

Useful contact numbers:

Contractor – JBA Bentley – Paul Craig – 07870 391 668

Environment Agency – Contact Centre – 03708 506 506

Parish Council           – Cllr Sara Haddon – 07808 958957
                                  – Cllr Roy Holloway – 01652 635 417

Week Beginning: 28th October 2019

No. of people on site (approx): 12

Social Media links:

Forecast lorry movements per day (approx): 10

South Ferriby Residents Group

Traffic Movement

  • All Clear 0% 0%
  • Some Lorries 40% 40%
  • Lots of Lorries 0% 0%
  • Temporary Traffic Lights 40% 40%
  • Road Closures 0% 0%

Please drive carefully when you see contractors working close to the side of the road

Outline of work to be undertaken this week

If the weather has allowed the completion of the east embankment we will be removing the concrete blocks from the side of the A1077 using temporary traffic lights for safety.

The earthworks equipment will be removed from the site working area as the earthworks will be paused over the winter period.

Useful contact numbers:

Contractor – JBA Bentley – Paul Craig – 07870 391 668

Environment Agency – Contact Centre – 03708 506 506

Parish Council           – Cllr Sara Haddon – 07808 958957
                                   – Cllr Roy Holloway – 01652 635 417

Week Beginning: 4th November 2019

No. of people on site (approx): 10

Social Media links:

Forecast lorry movements per day (approx): 10

South Ferriby Residents Group

Traffic Movement

  • All Clear 0% 0%
  • Some Lorries 40% 40%
  • Lots of Lorries 0% 0%
  • Temporary Traffic Lights 40% 40%
  • Road Closures 0% 0%

Please drive carefully when you see contractors working close to the side of the road

Outline of work to be undertaken this week

If the weather has allowed the completion of the east embankment we will continue to remove the concrete blocks from the side of the A1077 using temporary traffic lights for safety.

The working area known as compound six will be cleared and made safe ready for the winter shutdown.

 

Useful contact numbers:

Contractor – JBA Bentley – Paul Craig – 07870 391 668

Environment Agency – Contact Centre – 03708 506 506

Parish Council           – Cllr Sara Haddon – 07808 958957
                                   – Cllr Roy Holloway – 01652 635 417

Some parts of South Ferriby are at risk of flooding and with the advent of climate change and a greater focus on environmental issues the Parish Council has prepared a flood contingency plan for those living on lower ground.

Flood Protection Committee

The next Flood Protection Committee meeting will be held on Monday 21st October 2019,at 7.00pm in the Village Hall.
 
Agenda

 

Minutes

FPC Meeting – July 2019

FPC Meeting – April 2019

FPC Meeting – April 2018

FPC Meeting – January 2018

FPC Meeting – November 2017

FPC Meeting – September 2017

FPC meeting – July 2017

FPC meeting – June 2017

Flood Risk Contact List and Important Numbers

For more information about the flood plan contact Sara Haddon or Roy Hollaway via the Clerk on 07393 21 30 30 or by email

 

Emergency Telephone Numbers

South Ferriby Flood Wardens:

Roy Holloway 07899 906433
Dave Mouncey  07799 151255

North Lincolnshire Council  01724 297000
Environment Agency Floodline 0845 988 1188
Anglian Water 08457 919155

Contact the Clerk

Holly Hanson
Appledore
26 Main Street
Horkstow
Barton-upon-Humber
DN18 6BG

T: 07393 21 30 30