South Ferriby Flood Defences - Construction
Planning changes to Flood Defences – Improved traffic Restrictions – EA Engagement Video
Traffic Management Information
A lane closure to the eastbound side of the A1077 in the vicinity of the Sluice & Lock on the Ancolme has been scheduled for 14 weeks commencing 11th January 2021 to raise and strengthen flood defences to the North of the road
A Full Road Closure has been scheduled for the February 2021 Half Term starting Saturday 13th February for up to 7 days and programmed to be complete by Friday 19th February 2021.
There will still be some periods where there is one-way traffic either side of the road closure to install safety fencing to the verge of the road either side of CEMEX gate
Week Beginning: 4th January 2021
No. of people on site (approx): 15
Social Media links:
Forecast lorry movements per day (approx): 5
South Ferriby Residents Group
Traffic Movement
- All Clear 0%
- Some Lorries 40%
- Lots of Lorries 0%
- Temporary Traffic Lights 0%
- Road Closures 0%
Please drive carefully when you see contractors working close to the side of the road
Outline of work to be undertaken this week
Continue reinstatement works east and West of East Drain Bridge
Continue CEMEX Gate (South side off road) – Installation of running rail to open position and construction of winch plinths
Commence works to Sluice and Lock – enabling works only creating working area to West of sluice
Works around Fulseas Drain – NPG – Site Excavation/Cable Install – 6th/7th/8th January
Useful contact numbers:
Contractor – JBA Bentley – Tom Sherwood – 07870 391 668
Environment Agency – Contact Centre – 03708 506 506
Parish Council – Cllr Sara Haddon – 07808 958957
– Cllr Roy Holloway – 01652 635 417
Week Beginning: 11th January 2021
No. of people on site (approx): 16
Social Media links:
Forecast lorry movements per day (approx): 5
South Ferriby Residents Group
Traffic Movement
- All Clear 0%
- Some Lorries 40%
- Lots of Lorries 0%
- Temporary Traffic Lights 40%
- Road Closures 0%
Please drive carefully when you see contractors working close to the side of the road
Outline of work to be undertaken this week
Continue reinstatement works East and West of East Drain Bridge
Continue CEMEX Gate (South side off road) – Tidy area and prepare crane pads remove any temporary works
Works to Sluice and Lock – Installation of temporary traffic lights to eastbound lane over Sluice
Works to Sluice and Lock – Installation of scaffolding to northern Sluice parapet
Works to Sluice and Lock – works to raise existing concrete wall to West of Sluice / excavation to footing and installation of temporary platform
Works to Sluice and Lock – Enabling works to East of lock between lock and Hope & Anchor creating hardstanding area
Works around Fulseas Drain – NPG – Cable Jointing to energise the new cable – 11th January
Useful contact numbers:
Contractor – JBA Bentley – Tom Sherwood – 07970 532 127
Environment Agency – Contact Centre – 03708 506 506
Parish Council – Cllr Sara Haddon – 07808 958957
– Cllr Roy Holloway – 01652 635 417
Week Beginning: 18th January 2021
No. of people on site (approx): 17
Social Media links:
Forecast lorry movements per day (approx): 5
South Ferriby Residents Group
Traffic Movement
- All Clear 0%
- Some Lorries 40%
- Lots of Lorries 0%
- Temporary Traffic Lights 40%
- Road Closures 0%
Please drive carefully when you see contractors working close to the side of the road
Outline of work to be undertaken this week
Continue reinstatement works East and West of East Drain Bridge
Continue CEMEX Gate (South side off road) – Tidy area and prepare crane pads remove any temporary works
Works to Sluice and Lock – Commence works to strengthen northern Sluice parapet
Works to Sluice and Lock – Commence works to provide level foundations adjacent to lock for installation of demountable barriers to lock pier
Works to Sluice and Lock – works to raise existing concrete wall to West of Sluice / fix reinforcement and shutters to wall
Useful contact numbers:
Contractor – JBA Bentley – Tom Sherwood – 07970 532 127
Environment Agency – Contact Centre – 03708 506 506
Parish Council – Cllr Sara Haddon – 07808 958957
– Cllr Roy Holloway – 01652 635 417
Week Beginning: 14th December 2020
No. of people on site (approx): 14
Social Media links:
Forecast lorry movements per day (approx): 8
South Ferriby Residents Group
Traffic Movement
- All Clear 0%
- Some Lorries 40%
- Lots of Lorries 0%
- Temporary Traffic Lights 40%
- Road Closures 0%
Please drive carefully when you see contractors working close to the side of the road
Outline of work to be undertaken this week
Continue reinstatement works East and West of East Drain bridge
Continue works for CEMEX Gate South side carriageway – Complete reinforced concrete foundations and temporarily reinstate Sluice Road with tarmac – Westbound lane under traffic light control
CEMEX Gate South side carriageway – Remove Westbound lane traffic light control and re-open to two-way traffic at end of the week
Continue CEMEX Gate (South side off road) – reinforced concrete works to flood wall / gate open position foundation
Useful contact numbers:
Contractor – JBA Bentley – Tom Sherwood – 07970 532 127
Environment Agency – Contact Centre – 03708 506 506
Parish Council – Cllr Sara Haddon – 07808 958957
– Cllr Roy Holloway – 01652 635 417
Some parts of South Ferriby are at risk of flooding and with the advent of climate change and a greater focus on environmental issues the Parish Council has prepared a flood contingency plan for those living on lower ground.
Flood Protection Committee
Please click here to read the agenda
Minutes
Flood Risk Contact List and Important Numbers
For more information about the flood plan contact Sara Haddon or Roy Hollaway via the Clerk on 07393 21 30 30 or by email
Emergency Telephone Numbers
South Ferriby Flood Wardens:
Roy Holloway 07899 906433
Dave Mouncey 07799 151255
North Lincolnshire Council 01724 297000
Environment Agency Floodline 0845 988 1188
Anglian Water 08457 919155


Contact the Clerk
Holly Hanson
Appledore
26 Main Street
Horkstow
Barton-upon-Humber
DN18 6BG
T: 07393 21 30 30
