South Ferriby Flood Defences - Construction

Planning changes to Flood Defences – Improved traffic Restrictions – EA Engagement Video

 


Traffic Management Information

The Planning Application envisaged up to 30 weeks of road closures.

We are now advised by the Contractor that the actual time the road is closed will be no more than 7 days

There will still be some periods where there is one way traffic either side of the road closure

JBA Bentley are currently working on their work programme and need to satisfy the conditions attached to the planning application.

A lane closure to the eastbound then westbound side of the A1077 in the vicinity of the new CEMEX sliding gate has been scheduled for 11 weeks commencing 5th October 2020 to install the foundations for the new gate

Week Beginning: 19th October 2020

No. of people on site (approx): 22

Social Media links:

Forecast lorry movements per day (approx): 15

South Ferriby Residents Group

Traffic Movement

  • All Clear 0% 0%
  • Some Lorries 40% 40%
  • Lots of Lorries 0% 0%
  • Temporary Traffic Lights 40% 40%
  • Road Closures 0% 0%

Please drive carefully when you see contractors working close to the side of the road

Outline of work to be undertaken this week

Continue reinstatement works east and west of east drain bridge

Complete brickwork to wall construction east and west of east drain bridge

Commence wet side maintenance path to east side of east drain

Install flood gate in wall to west of east drain wall

Continue works around Fulseas drain dry side drainage, earthworks and reinstatement

Continue installation of dry side drainage to East bank (access dependent)

Continue works for CEMEX Gate North side – Excavation in road and verge for Reinforced concrete gate foundations and continue with piling mat – Eastbound lane under traffic light control

Continue CEMEX Gate (South side off road) – reinforced concrete works to flood wall / gate open position foundation

Useful contact numbers:

Contractor – JBA Bentley – Tom Sherwood – 07870 391 668

Environment Agency – Contact Centre – 03708 506 506

Parish Council           – Cllr Sara Haddon – 07808 958957
                                  – Cllr Roy Holloway – 01652 635 417

Week Beginning: 26th October 2020

No. of people on site (approx): 22

Social Media links:

Forecast lorry movements per day (approx): 15

South Ferriby Residents Group

Traffic Movement

  • All Clear 0% 0%
  • Some Lorries 40% 40%
  • Lots of Lorries 0% 0%
  • Temporary Traffic Lights 40% 40%
  • Road Closures 0% 0%

Please drive carefully when you see contractors working close to the side of the road

Outline of work to be undertaken this week

Continue reinstatement works east and west of east drain bridge

Commence Copings to wall construction east and west of east drain bridge

Continue wet side maintenance path to east and west side of east drain

Continue works around Fulseas drain dry side drainage, earthworks and reinstatement

Continue installation of dry side drainage to East bank (access dependent)

Continue works for CEMEX Gate North side – Installation of mini piles for gate foundations and sheet pile tie in from gate to embankment – Eastbound lane under traffic light control

Continue CEMEX Gate (South side off road) – reinforced concrete works to flood wall / gate open position foundation & installation of sheet pile tie in from gate to embankment

Useful contact numbers:

Contractor – JBA Bentley – Tom Sherwood – 07970 532 127

Environment Agency       – Contact Centre – 03708 506 506

Parish Council                 – Cllr Sara Haddon – 07808 958957
– Cllr Roy Holloway – 01652 635 417

Week Beginning: 2nd November 2020

No. of people on site (approx): 22

Social Media links:

Forecast lorry movements per day (approx): 15

South Ferriby Residents Group

Traffic Movement

  • All Clear 0% 0%
  • Some Lorries 40% 40%
  • Lots of Lorries 0% 0%
  • Temporary Traffic Lights 40% 40%
  • Road Closures 0% 0%

Please drive carefully when you see contractors working close to the side of the road

Outline of work to be undertaken this week

Continue reinstatement works east and west of east drain bridge

Continue Copings to wall construction east and west of east drain bridge

Continue works around Fulseas drain dry side drainage, earthworks and reinstatement

Commence fencing to Area around east bank

Continue installation of dry side drainage to East bank (access dependent)

Continue works for CEMEX Gate North side – Reinforced concrete gate foundations – Eastbound lane under traffic light control

Continue CEMEX Gate (South side off road) – reinforced concrete works to flood wall / gate open position foundation

Useful contact numbers:

Contractor – JBA Bentley – Tom Sherwood – 07970 532 127

Environment Agency       – Contact Centre – 03708 506 506

Parish Council                 – Cllr Sara Haddon – 07808 958957
– Cllr Roy Holloway – 01652 635 417

Week Beginning: 9th November 2020

No. of people on site (approx): 22

Social Media links:

Forecast lorry movements per day (approx): 15

South Ferriby Residents Group

Traffic Movement

  • All Clear 0% 0%
  • Some Lorries 40% 40%
  • Lots of Lorries 0% 0%
  • Temporary Traffic Lights 40% 40%
  • Road Closures 0% 0%

Please drive carefully when you see contractors working close to the side of the road

Outline of work to be undertaken this week

Continue reinstatement works east and west of east drain bridge

Complete works around Fulseas drain reinstatement for 2020

Continue fencing to Area around east bank

Complete installation of dry side drainage to East bank (access dependent)

Continue works for CEMEX Gate North side – Reinforced concrete gate foundations – Eastbound lane under traffic light control

Continue CEMEX Gate (South side off road) – reinforced concrete works to flood wall / gate open position foundation

Useful contact numbers:

Contractor – JBA Bentley – Tom Sherwood – 07970 532 127

Environment Agency       – Contact Centre – 03708 506 506

Parish Council                 – Cllr Sara Haddon – 07808 958957
– Cllr Roy Holloway – 01652 635 417

Some parts of South Ferriby are at risk of flooding and with the advent of climate change and a greater focus on environmental issues the Parish Council has prepared a flood contingency plan for those living on lower ground.

Flood Risk Contact List and Important Numbers

For more information about the flood plan contact Sara Haddon or Roy Hollaway via the Clerk on 07393 21 30 30 or by email

 

Emergency Telephone Numbers

South Ferriby Flood Wardens:

Roy Holloway 07899 906433
Dave Mouncey  07799 151255

North Lincolnshire Council  01724 297000
Environment Agency Floodline 0845 988 1188
Anglian Water 08457 919155

Contact the Clerk

Holly Hanson
Appledore
26 Main Street
Horkstow
Barton-upon-Humber
DN18 6BG

T: 07393 21 30 30