South Ferriby Flood Defences - Construction

Andrew Percy visited the South Ferriby Flood Defence works on Friday 12th July to check on progress for the project.  Please click here for the visit update.

Traffic Management Information

We will be carrying out some trial hole excavation work in the road on the East Drain Bridge just east of the Hope and Anchor Pub week commencing Monday 19th August.
This work will required the use of temporary traffic lights in order to protect the work force. The temporary lights will not be in operation during rush hour periods.
The lights will be in operation from 9.30am until 3.30pm for a maximum of 2 weeks.

The Planning Application envisaged up to 30 weeks of road closures.

We are now advised by the Contractor that the actual time the road is closed will,be significantly less than this.

JBA Bentley are currently working on their work programme and need to satisfy the conditions attached to the planning application.

We can confirm that there will be no road closures during 2019

Future Works Programme

July 2019 to October 2019 – East Embankment (East Drain to Lowish Farm)

April 2020 – June 2020 – West Embankment (Section around CEMEX football pitch)

April 2020 to September 2020 CEMEX Embankment

September 2019 to June 2020 – Hard defences from Sluice to East Drain tie in with the embankment

Week Beginning: 19th August 2019

No. of people on site (approx): 15

Social Media links:

Forecast lorry movements per day (approx): 180

South Ferriby Residents Group

Traffic Movement

  • All Clear 0% 0%
  • Some Lorries 0% 0%
  • Lots of Lorries 40% 40%
  • Temporary Traffic Lights 40% 40%
  • Road Closures 0% 0%

Please drive carefully when you see contractors working close to the side of the road

Outline of work to be undertaken this week

The transportation of clay from the CEMEX plant will continue along Sluice Road to be stored in compound 6.

We will continue to place clay in compacted layers to create the flood bund.

We will be placing topsoil to the sides of the new flood bank and hardcore to the top to create a running surface to be used for EA maintenance access.

We will be digging trial holes in the A1077 in the location of the East Drain bridge. This work will required temporary traffic lights.

Useful contact numbers:

Contractor – JBA Bentley – Paul Craig – 07870 391 668

Environment Agency – Contact Centre – 03708 506 506

Parish Council           – Cllr Sara Haddon – 07808 958957
                                  – Cllr Roy Holloway – 01652 635 417

Week Beginning: 26th August 2019

No. of people on site (approx): 15

Social Media links:

Forecast lorry movements per day (approx): 5

South Ferriby Residents Group

Traffic Movement

  • All Clear 0% 0%
  • Some Lorries 40% 40%
  • Lots of Lorries 0% 0%
  • Temporary Traffic Lights 40% 40%
  • Road Closures 0% 0%

Please drive carefully when you see contractors working close to the side of the road

Outline of work to be undertaken this week

We will continue to place clay in compacted layers to create the flood bund.

We will be placing topsoil to the sides of the new flood bank and hardcore to the top to create a running surface to be used for EA maintenance access.

We will be digging trial holes in the A1077 in the location of the East Drain bridge. This work will required temporary traffic lights.

Useful contact numbers:

Contractor – JBA Bentley – Paul Craig – 07870 391 668

Environment Agency – Contact Centre – 03708 506 506

Parish Council           – Cllr Sara Haddon – 07808 958957
                                   – Cllr Roy Holloway – 01652 635 417

Week Beginning: 2nd September 2019

No. of people on site (approx): 15

Social Media links:

Forecast lorry movements per day (approx): 5

South Ferriby Residents Group

Traffic Movement

  • All Clear 0% 0%
  • Some Lorries 40% 40%
  • Lots of Lorries 0% 0%
  • Temporary Traffic Lights 0% 0%
  • Road Closures 0% 0%

Please drive carefully when you see contractors working close to the side of the road

Outline of work to be undertaken this week

We will continue to place clay in compacted layers to create the flood bund.

We will be placing topsoil to the sides of the new flood bank and hardcore to the top to create a running surface to be used for EA maintenance access.

Useful contact numbers:

Contractor – JBA Bentley – Paul Craig – 07870 391 668

Environment Agency – Contact Centre – 03708 506 506

Parish Council           – Cllr Sara Haddon – 07808 958957
                                   – Cllr Roy Holloway – 01652 635 417

Some parts of South Ferriby are at risk of flooding and with the advent of climate change and a greater focus on environmental issues the Parish Council has prepared a flood contingency plan for those living on lower ground.

Flood Protection Committee

The next Flood Protection Committee meeting will be held on Monday 21st October 2019,at 7.00pm in the Village Hall.
 
Agenda

 

Minutes

FPC Meeting – July 2019

FPC Meeting – April 2019

FPC Meeting – April 2018

FPC Meeting – January 2018

FPC Meeting – November 2017

FPC Meeting – September 2017

FPC meeting – July 2017

FPC meeting – June 2017

Flood Risk Contact List and Important Numbers

For more information about the flood plan contact Sara Haddon or Roy Hollaway via the Clerk on 07393 21 30 30 or by email

 

Emergency Telephone Numbers

South Ferriby Flood Wardens:

Roy Holloway 07899 906433
Dave Mouncey  07799 151255

North Lincolnshire Council  01724 297000
Environment Agency Floodline 0845 988 1188
Anglian Water 08457 919155

Contact the Clerk

Holly Hanson
Appledore
26 Main Street
Horkstow
Barton-upon-Humber
DN18 6BG

T: 07393 21 30 30