South Ferriby Flood Defences - Construction

Planning changes to Flood Defences – Improved traffic Restrictions – EA Engagement Video

 


Traffic Management Information

A lane closure to the eastbound side of the A1077 in the vicinity of the Sluice & Lock on the Ancolme has been scheduled for 14 weeks commencing 11th January 2021 to raise and strengthen flood defences to the North of the road

A Full Road Closure has been scheduled for the February 2021 Half Term starting Saturday 13th February for up to 7 days and programmed to be complete by Friday 19th February 2021.

There will still be some periods where there is one-way traffic either side of the road closure to install safety fencing to the verge of the road either side of CEMEX gate

Week Beginning: 4th January 2021

No. of people on site (approx): 15

Social Media links:

Forecast lorry movements per day (approx): 5

South Ferriby Residents Group

Traffic Movement

  • All Clear 0% 0%
  • Some Lorries 40% 40%
  • Lots of Lorries 0% 0%
  • Temporary Traffic Lights 0% 0%
  • Road Closures 0% 0%

Please drive carefully when you see contractors working close to the side of the road

Outline of work to be undertaken this week

Continue reinstatement works east and West of East Drain Bridge

Continue CEMEX Gate (South side off road) – Installation of running rail to open position and construction of winch plinths

Commence works to Sluice and Lock – enabling works only creating working area to West of sluice

Works around Fulseas Drain – NPG – Site Excavation/Cable Install – 6th/7th/8th January

Useful contact numbers:

Contractor – JBA Bentley – Tom Sherwood – 07870 391 668

Environment Agency – Contact Centre – 03708 506 506

Parish Council           – Cllr Sara Haddon – 07808 958957
                                  – Cllr Roy Holloway – 01652 635 417

Week Beginning: 11th January 2021

No. of people on site (approx): 16

Social Media links:

Forecast lorry movements per day (approx): 5

South Ferriby Residents Group

Traffic Movement

  • All Clear 0% 0%
  • Some Lorries 40% 40%
  • Lots of Lorries 0% 0%
  • Temporary Traffic Lights 40% 40%
  • Road Closures 0% 0%

Please drive carefully when you see contractors working close to the side of the road

Outline of work to be undertaken this week

Continue reinstatement works East and West of East Drain Bridge

Continue CEMEX Gate (South side off road) – Tidy area and prepare crane pads remove any temporary works

Works to Sluice and Lock – Installation of temporary traffic lights to eastbound lane over Sluice

Works to Sluice and Lock – Installation of scaffolding to northern Sluice parapet

Works to Sluice and Lock – works to raise existing concrete wall to West of Sluice / excavation to footing and installation of temporary platform

Works to Sluice and Lock – Enabling works to East of lock between lock and Hope & Anchor creating hardstanding area

Works around Fulseas Drain – NPG – Cable Jointing to energise the new cable – 11th January

Useful contact numbers:

Contractor – JBA Bentley – Tom Sherwood – 07970 532 127

Environment Agency       – Contact Centre – 03708 506 506

Parish Council                 – Cllr Sara Haddon – 07808 958957
– Cllr Roy Holloway – 01652 635 417

Week Beginning: 18th January 2021

No. of people on site (approx): 17

Social Media links:

Forecast lorry movements per day (approx): 5

South Ferriby Residents Group

Traffic Movement

  • All Clear 0% 0%
  • Some Lorries 40% 40%
  • Lots of Lorries 0% 0%
  • Temporary Traffic Lights 40% 40%
  • Road Closures 0% 0%

Please drive carefully when you see contractors working close to the side of the road

Outline of work to be undertaken this week

Continue reinstatement works East and West of East Drain Bridge

Continue CEMEX Gate (South side off road) – Tidy area and prepare crane pads remove any temporary works

Works to Sluice and Lock – Commence works to strengthen northern Sluice parapet

Works to Sluice and Lock – Commence works to provide level foundations adjacent to lock for installation of demountable barriers to lock pier

Works to Sluice and Lock – works to raise existing concrete wall to West of Sluice / fix reinforcement and shutters to wall

Useful contact numbers:

Contractor – JBA Bentley – Tom Sherwood – 07970 532 127

Environment Agency       – Contact Centre – 03708 506 506

Parish Council                 – Cllr Sara Haddon – 07808 958957
– Cllr Roy Holloway – 01652 635 417

Week Beginning: 14th December 2020

No. of people on site (approx): 14

Social Media links:

Forecast lorry movements per day (approx): 8

South Ferriby Residents Group

Traffic Movement

  • All Clear 0% 0%
  • Some Lorries 40% 40%
  • Lots of Lorries 0% 0%
  • Temporary Traffic Lights 40% 40%
  • Road Closures 0% 0%

Please drive carefully when you see contractors working close to the side of the road

Outline of work to be undertaken this week

Continue reinstatement works East and West of East Drain bridge

Continue works for CEMEX Gate South side carriageway – Complete reinforced concrete foundations and temporarily reinstate Sluice Road with tarmac – Westbound lane under traffic light control

CEMEX Gate South side carriageway – Remove Westbound lane traffic light control and re-open to two-way traffic at end of the week

Continue CEMEX Gate (South side off road) – reinforced concrete works to flood wall / gate open position foundation

Useful contact numbers:

Contractor – JBA Bentley – Tom Sherwood – 07970 532 127

Environment Agency       – Contact Centre – 03708 506 506

Parish Council                 – Cllr Sara Haddon – 07808 958957
– Cllr Roy Holloway – 01652 635 417

Some parts of South Ferriby are at risk of flooding and with the advent of climate change and a greater focus on environmental issues the Parish Council has prepared a flood contingency plan for those living on lower ground.

Flood Risk Contact List and Important Numbers

For more information about the flood plan contact Sara Haddon or Roy Hollaway via the Clerk on 07393 21 30 30 or by email

 

Emergency Telephone Numbers

South Ferriby Flood Wardens:

Roy Holloway 07899 906433
Dave Mouncey  07799 151255

North Lincolnshire Council  01724 297000
Environment Agency Floodline 0845 988 1188
Anglian Water 08457 919155

Contact the Clerk

Holly Hanson
Appledore
26 Main Street
Horkstow
Barton-upon-Humber
DN18 6BG

T: 07393 21 30 30