South Ferriby Flood Defences - Construction

Planning changes to Flood Defences – Improved traffic Restrictions – EA Engagement Video

 


Traffic Management Information

The Planning Application envisaged up to 30 weeks of road closures.

We are now advised by the Contractor that the actual time the road is closed will be no more than 7 days.

There will still be some periods where there is one-way traffic either side of the road closure.

A lane closure to the eastbound then Westbound side of the A1077 in the vicinity of the new CEMEX sliding gate has been scheduled for 11 weeks commencing 5th October 2020 to install the foundations for the new gate

A lane closure to the Eastbound side of the A1077 in the vicinity of the Sluice & Lock on the Ancolme has been scheduled for 14 weeks commencing 11th January 2021 to raise and strengthen flood defences to the North of the road

A Full Road Closure has been scheduled for the February 2021 Half Term starting Saturday 13th February for up to 7 days and programmed to be complete by Friday 19th February 2021.

Week Beginning: 23rd November 2020

No. of people on site (approx): 22

Social Media links:

Forecast lorry movements per day (approx): 15

South Ferriby Residents Group

Traffic Movement

  • All Clear 0% 0%
  • Some Lorries 40% 40%
  • Lots of Lorries 0% 0%
  • Temporary Traffic Lights 40% 40%
  • Road Closures 0% 0%

Please drive carefully when you see contractors working close to the side of the road

Outline of work to be undertaken this week

Continue reinstatement works East and West of East Drain bridge

Continue works around Fulseas Drain reinstatement

Continue installation of dry side drainage to East bank

Continue fencing to area around East bank

CEMEX Gate – With traffic management from Eastbound to Westbound under traffic light control

Commence works for CEMEX Gate South side carriageway – Excavation of carriageway / prove services and prepare piling mat – Westbound lane under traffic light control

Continue CEMEX Gate (South side off road) – reinforced concrete works to flood wall / gate open position foundation

Useful contact numbers:

Contractor – JBA Bentley – Tom Sherwood – 07870 391 668

Environment Agency – Contact Centre – 03708 506 506

Parish Council           – Cllr Sara Haddon – 07808 958957
                                  – Cllr Roy Holloway – 01652 635 417

Week Beginning: 30th November 2020

No. of people on site (approx): 22

Social Media links:

Forecast lorry movements per day (approx): 15

South Ferriby Residents Group

Traffic Movement

  • All Clear 0% 0%
  • Some Lorries 40% 40%
  • Lots of Lorries 0% 0%
  • Temporary Traffic Lights 40% 40%
  • Road Closures 0% 0%

Please drive carefully when you see contractors working close to the side of the road

Outline of work to be undertaken this week

Continue reinstatement works East and West of East Drain bridge

Complete works around Fulseas Drain reinstatement and demobilise site welfare (Note return visit in spring for final tidy up / remove surplus clay)

Final Reinstatements following dry side drainage to East bank depending on weather and ground conditions. (Possible return visit in spring for final finishings)

Continue fencing to area around East bank.

Continue works for CEMEX Gate South side carriageway – Installation of mini piles and commence reinforced concrete foundations – Westbound lane under traffic light control

Continue CEMEX Gate (South side off road) – reinforced concrete works to flood wall / gate open position foundation

Useful contact numbers:

Contractor – JBA Bentley – Tom Sherwood – 07970 532 127

Environment Agency       – Contact Centre – 03708 506 506

Parish Council                 – Cllr Sara Haddon – 07808 958957
– Cllr Roy Holloway – 01652 635 417

Week Beginning: 7th December 2020

No. of people on site (approx): 22

Social Media links:

Forecast lorry movements per day (approx): 15

South Ferriby Residents Group

Traffic Movement

  • All Clear 0% 0%
  • Some Lorries 40% 40%
  • Lots of Lorries 0% 0%
  • Temporary Traffic Lights 40% 40%
  • Road Closures 0% 0%

Please drive carefully when you see contractors working close to the side of the road

Outline of work to be undertaken this week

Continue reinstatement works East and West of East Drain bridge

Continue fencing to area around East bank. First phase should be complete (Return visit in Spring for final connections)

Continue works for CEMEX Gate South side carriageway – Continue reinforced concrete foundations – Westbound lane under traffic light control

Continue CEMEX Gate (South side off road) – reinforced concrete works to flood wall / gate open position foundation

Useful contact numbers:

Contractor – JBA Bentley – Tom Sherwood – 07970 532 127

Environment Agency       – Contact Centre – 03708 506 506

Parish Council                 – Cllr Sara Haddon – 07808 958957
– Cllr Roy Holloway – 01652 635 417

Week Beginning: 14th December 2020

No. of people on site (approx): 14

Social Media links:

Forecast lorry movements per day (approx): 8

South Ferriby Residents Group

Traffic Movement

  • All Clear 0% 0%
  • Some Lorries 40% 40%
  • Lots of Lorries 0% 0%
  • Temporary Traffic Lights 40% 40%
  • Road Closures 0% 0%

Please drive carefully when you see contractors working close to the side of the road

Outline of work to be undertaken this week

Continue reinstatement works East and West of East Drain bridge

Continue works for CEMEX Gate South side carriageway – Complete reinforced concrete foundations and temporarily reinstate Sluice Road with tarmac – Westbound lane under traffic light control

CEMEX Gate South side carriageway – Remove Westbound lane traffic light control and re-open to two-way traffic at end of the week

Continue CEMEX Gate (South side off road) – reinforced concrete works to flood wall / gate open position foundation

Useful contact numbers:

Contractor – JBA Bentley – Tom Sherwood – 07970 532 127

Environment Agency       – Contact Centre – 03708 506 506

Parish Council                 – Cllr Sara Haddon – 07808 958957
– Cllr Roy Holloway – 01652 635 417

Week Beginning: 21st December 2020

No. of people on site (approx): 5

Social Media links:

Forecast lorry movements per day (approx): 5

South Ferriby Residents Group

Traffic Movement

  • All Clear 0% 0%
  • Some Lorries 40% 40%
  • Lots of Lorries 0% 0%
  • Temporary Traffic Lights 0% 0%
  • Road Closures 0% 0%

Please drive carefully when you see contractors working close to the side of the road

Outline of work to be undertaken this week

Limited works / workforce (working only Monday 21st and Tuesday 22nd) – Site tidy / check security of fencing / break up for Christmas Break

JN Bentley On Annual leave 23rd December 2020 to Sunday 3rd January 2021 inclusive returning Monday 4th January 2021

We hope all the residents of South Ferriby have a Merry Christmas and Happy New Year

Useful contact numbers:

Contractor – JBA Bentley – Tom Sherwood – 07970 532 127

Environment Agency       – Contact Centre – 03708 506 506

Parish Council                 – Cllr Sara Haddon – 07808 958957
– Cllr Roy Holloway – 01652 635 417

Some parts of South Ferriby are at risk of flooding and with the advent of climate change and a greater focus on environmental issues the Parish Council has prepared a flood contingency plan for those living on lower ground.

Flood Risk Contact List and Important Numbers

For more information about the flood plan contact Sara Haddon or Roy Hollaway via the Clerk on 07393 21 30 30 or by email

 

Emergency Telephone Numbers

South Ferriby Flood Wardens:

Roy Holloway 07899 906433
Dave Mouncey  07799 151255

North Lincolnshire Council  01724 297000
Environment Agency Floodline 0845 988 1188
Anglian Water 08457 919155

Contact the Clerk

Holly Hanson
Appledore
26 Main Street
Horkstow
Barton-upon-Humber
DN18 6BG

T: 07393 21 30 30