Flood Defences
South Ferriby Flood Defences – Construction
Planning changes to Flood Defences – Improved traffic Restrictions – EA Engagement Video
Traffic Management Information
A lane closure to the eastbound side of the A1077 in the vicinity of the Sluice & Lock on the Ancolme has been scheduled for 14 weeks commencing 11th January 2021 to raise and strengthen flood defences to the North of the road
A Full Road Closure has been scheduled for the February 2021 Half Term starting Saturday 13th February for up to 7 days and programmed to be complete by Friday 19th February 2021.
There will still be some periods where there is one-way traffic either side of the road closure to install safety fencing to the verge of the road either side of CEMEX gate.
Week Beginning: 18th January 2021
No. of people on site (approx): 17
Social Media links:
Forecast lorry movements per day (approx): 5
South Ferriby Residents Group
Traffic Movement
- All Clear 0%
- Some Lorries 40%
- Lots of Lorries 0%
- Temporary Traffic Lights 40%
- Road Closures 0%
Please drive carefully when you see contractors working close to the side of the road
Outline of work to be undertaken this week
Continue reinstatement works east of East Drain bridge (weather dependent)
Continue CEMEX Gate (South side off road) – Tidy area and prepare crane pads remove any temporary works
Works to Sluice and Lock – Commence works to strengthen northern sluice parapet
Works to Sluice and Lock – Commence works to provide level foundations adjacent to lock for installation of demountable barriers to lock pier
Works to Sluice and Lock – Works to raise existing concrete wall to west of sluice / fix reinforcement and shutters to wall and concrete to same
Useful contact numbers:
Contractor – JBA Bentley – Tom Sherwood – 07870 391 668
Environment Agency – Contact Centre – 03708 506 506
Parish Council – Cllr Sara Haddon – 07808 958957
– Cllr Roy Holloway – 01652 635 417
Week Beginning: 25th January 2021
No. of people on site (approx): 17
Social Media links:
Forecast lorry movements per day (approx): 5
South Ferriby Residents Group
Traffic Movement
- All Clear 0%
- Some Lorries 40%
- Lots of Lorries 0%
- Temporary Traffic Lights 40%
- Road Closures 0%
Please drive carefully when you see contractors working close to the side of the road
Outline of work to be undertaken this week
Continue reinstatement works east of East Drain bridge and East Drain bridge copings (weather dependent)
Continue CEMEX Gate (South side off road) – minor works / rubbing up / winch plinths / preparation for road closure
Works to Sluice and Lock – Continue works to strengthen northern sluice parapet
Works to Sluice and Lock – Continue works to east of lock construction of flood defences
Works to Sluice and Lock – Works to raise existing concrete wall to west of sluice / fix reinforcement and shutters to wall and concrete to same
Useful contact numbers:
Contractor – JBA Bentley – Tom Sherwood – 07970 532 127
Environment Agency – Contact Centre – 03708 506 506
Parish Council – Cllr Sara Haddon – 07808 958957
– Cllr Roy Holloway – 01652 635 417
Week Beginning: 1st February 2021
No. of people on site (approx): 17
Social Media links:
Forecast lorry movements per day (approx): 5
South Ferriby Residents Group
Traffic Movement
- All Clear 0%
- Some Lorries 40%
- Lots of Lorries 0%
- Temporary Traffic Lights 40%
- Road Closures 0%
Please drive carefully when you see contractors working close to the side of the road
Outline of work to be undertaken this week
Continue reinstatement works east of East Drain bridge and East Drain bridge copings (weather dependent)
Continue CEMEX Gate (South side off road) – minor works / rubbing up / winch plinths / preparation for road closure
Works to Sluice and Lock – Complete works to strengthen northern sluice parapet
Works to Sluice and Lock – Continue works to east of lock construction of flood defences
Works to Sluice and Lock – Works to raise existing concrete wall to west of sluice / fix reinforcement and shutters to wall and concrete to same
Useful contact numbers:
Contractor – JBA Bentley – Tom Sherwood – 07970 532 127
Environment Agency – Contact Centre – 03708 506 506
Parish Council – Cllr Sara Haddon – 07808 958957
– Cllr Roy Holloway – 01652 635 417
Week Beginning: 8th February 2021
No. of people on site (approx): 17
Social Media links:
Forecast lorry movements per day (approx): 5
South Ferriby Residents Group
Traffic Movement
- All Clear 0%
- Some Lorries 40%
- Lots of Lorries 0%
- Temporary Traffic Lights 40%
- Road Closures 0%
Please drive carefully when you see contractors working close to the side of the road
Outline of work to be undertaken this week
Continue reinstatement works east of East Drain bridge and East Drain bridge copings (weather dependent)
Continue CEMEX Gate (South side off road) – minor works / rubbing up / winch plinths / preparation for road closure
A Full Road Closure to Sluice road at CEMEX Gate commences Saturday 13th February for up to 7 days.
Works to Sluice and Lock – Remove scaffolding from sluice parapet
Works to Sluice and Lock – Continue works to east of lock construction of flood defences
Works to Sluice and Lock – make good all area to west of Sluice
Useful contact numbers:
Contractor – JBA Bentley – Tom Sherwood – 07970 532 127
Environment Agency – Contact Centre – 03708 506 506
Parish Council – Cllr Sara Haddon – 07808 958957
– Cllr Roy Holloway – 01652 635 417
Week Beginning: 15th February 2021
No. of people on site (approx): 19
Social Media links:
Forecast lorry movements per day (approx): 5
South Ferriby Residents Group
Traffic Movement
- All Clear 0%
- Some Lorries 40%
- Lots of Lorries 0%
- Temporary Traffic Lights 40%
- Road Closures 40%
Please drive carefully when you see contractors working close to the side of the road
Outline of work to be undertaken this week
Continue reinstatement works east of East Drain bridge and East Drain bridge copings (weather dependent)
Continue CEMEX Gate – A Full Road Closure to Sluice road at CEMEX Gate commences Saturday 13th February for up to 7 days for installation of the flood gate running rail, flood gate and associated resurfacing works
Works to Sluice and Lock – Continue works to east of lock construction of flood defences
Works to Sluice and Lock – works to raise existing concrete wall to west of sluice / fix reinforcement and shutters to wall
Useful contact numbers:
Contractor – JBA Bentley – Tom Sherwood – 07970 532 127
Environment Agency – Contact Centre – 03708 506 506
Parish Council – Cllr Sara Haddon – 07808 958957
– Cllr Roy Holloway – 01652 635 417
South Ferriby Flood Defences – Additional Information
Some parts of South Ferriby are at risk of flooding and with the advent of climate change and a greater focus on environmental issues the Parish Council has prepared a flood contingency plan for those living on lower ground.
Flood Protection Committee
The next Flood Protection Committee meeting will be held on Monday 25th January 2021 at 7.00pm via a WHYPAY conference call.
Please click here to read the agenda Opens in a new window
Minutes
FPC Meeting – November 2020 Opens in a new window
FPC Meeting – September 2020 Opens in a new window
FPC Meeting – June 2020 Opens in a new window
FPC Meeting – February 2020 Opens in a new window
FPC Meeting – October 2019 Opens in a new window
FPC Meeting – July 2019 Opens in a new window
FPC Meeting – April 2019 Opens in a new window
FPC Meeting – April 2018 Opens in a new window
FPC Meeting – January 2018 Opens in a new window
FPC Meeting – November 2017 Opens in a new window
FPC Meeting – September 2017 Opens in a new window
Flood Risk Contact List and Important Numbers
For more information about the flood plan contact Sara Haddon or Roy Hollaway via the Clerk on 07393 21 30 30 or by email May open an email client if one is installed.
Emergency Numbers
South Ferriby Flood Wardens
Roy Holloway 07899 906 433
Dave Mouncey 07799 151 255
Miscellaneous
North Lincolnshire Council 01724 297 000
Environment Agency Floodline 0845 988 1188
Anglian Water 08457 919 155
Clerk
Holly Hanson
Appledore, 26 Main Street, Horkstow
Barton-upon-Humber DN18 6BG
Telephone
07393 21 30 30
