South Ferriby Flood Defences - Construction

Planning changes to Flood Defences – Improved traffic Restrictions – EA Engagement Video

 


Traffic Management Information

The Planning Application envisaged up to 30 weeks of road closures.

We are now advised by the Contractor that the actual time the road is closed will be no more than 7 days

There will still be some periods where there is one-way traffic either side of the road closure

JBA Bentley are currently working on their work programme and need to satisfy the conditions attached to the planning application.

A lane closure to the eastbound side of the A1077 in the vicinity of the east drain has been scheduled for 9 weeks commencing 15th June 2020 to complete the raising of the defences to the east drain bridge

Week Beginning: 20th July 2020

No. of people on site (approx): 24

Social Media links:

Forecast lorry movements per day (approx): 20

South Ferriby Residents Group

Traffic Movement

  • All Clear 0% 0%
  • Some Lorries 40% 40%
  • Lots of Lorries 0% 0%
  • Temporary Traffic Lights 40% 40%
  • Road Closures 0% 0%

Please drive carefully when you see contractors working close to the side of the road

Outline of work to be undertaken this week

Continue with new wall construction east of east drain bridge

Continue works to flood defence wall to west of East Drain

Continue works at East Drain Bridge to raise remove and raise existing parapet wall. Works will involve a lane closure under traffic light control to the eastbound carriageway

Continue construction of CEMEX embankment from Ch250 to 750 and placing topsoil to banks

Commence works to Fulseas drain replacement

Useful contact numbers:

Contractor – JBA Bentley – Tom Sherwood – 07870 391 668

Environment Agency – Contact Centre – 03708 506 506

Parish Council           – Cllr Sara Haddon – 07808 958957
– Cllr Roy Holloway – 01652 635 417

Week Beginning: 27th July 2020

No. of people on site (approx): 24

Social Media links:

Forecast lorry movements per day (approx): 20

South Ferriby Residents Group

Traffic Movement

  • All Clear 0% 0%
  • Some Lorries 40% 40%
  • Lots of Lorries 0% 0%
  • Temporary Traffic Lights 40% 40%
  • Road Closures 0% 0%

Please drive carefully when you see contractors working close to the side of the road

Outline of work to be undertaken this week

Continue with new wall construction east of east drain bridge

Continue works to flood defence wall to west of East Drain

Continue works at East Drain Bridge to raise remove and raise existing parapet wall. Works will involve a lane closure under traffic light control to the eastbound carriageway

Continue construction of CEMEX embankment from Ch500 to 750 and placing topsoil to banks

Continue works to Fulseas drain replacement

Ground Investigation around the area of The Hope & Anchor

Useful contact numbers:

Contractor – JBA Bentley – Tom Sherwood – 07870 391 668

Environment Agency – Contact Centre – 03708 506 506

Parish Council           – Cllr Sara Haddon – 07808 958957
                                   – Cllr Roy Holloway – 01652 635 417

Week Beginning: 3rd August 2020

No. of people on site (approx): 24

Social Media links:

Forecast lorry movements per day (approx): 20

South Ferriby Residents Group

Traffic Movement

  • All Clear 0% 0%
  • Some Lorries 40% 40%
  • Lots of Lorries 0% 0%
  • Temporary Traffic Lights 40% 40%
  • Road Closures 0% 0%

Please drive carefully when you see contractors working close to the side of the road

Outline of work to be undertaken this week

Continue with new wall construction east of east drain bridge

Continue works to flood defence wall to west of East Drain

Continue works at East Drain Bridge to raise remove and raise existing parapet wall. Works will involve a lane closure under traffic light control to the eastbound carriageway

Continue construction of CEMEX embankment from Ch500 to 750 and placing topsoil to banks

Continue works to Fulseas drain replacement and embankment reconstruction

Useful contact numbers:

Contractor – JBA Bentley – Tom Sherwood – 07870 391 668

Environment Agency – Contact Centre – 03708 506 506

Parish Council           – Cllr Sara Haddon – 07808 958957
                                  – Cllr Roy Holloway – 01652 635 417

Some parts of South Ferriby are at risk of flooding and with the advent of climate change and a greater focus on environmental issues the Parish Council has prepared a flood contingency plan for those living on lower ground.

Flood Risk Contact List and Important Numbers

For more information about the flood plan contact Sara Haddon or Roy Hollaway via the Clerk on 07393 21 30 30 or by email

 

Emergency Telephone Numbers

South Ferriby Flood Wardens:

Roy Holloway 07899 906433
Dave Mouncey  07799 151255

North Lincolnshire Council  01724 297000
Environment Agency Floodline 0845 988 1188
Anglian Water 08457 919155

Contact the Clerk

Holly Hanson
Appledore
26 Main Street
Horkstow
Barton-upon-Humber
DN18 6BG

T: 07393 21 30 30