South Ferriby Flood Defences - Construction

Traffic Management Information

The Planning Application envisaged up to 30 weeks of road closures.

We are now advised by the Contractor that the actual time the road is closed will, be significantly less than this.

JBA Bentley are currently working on their work programme and need to satisfy the conditions attached to the planning application.

A lane closure to the eastbound side of the A1077 in the vicinity of the east drain has been scheduled for 9 weeks commencing 15th June 2020 to complete the raising of the defences to the east drain bridge.

Week Beginning: 8th June 2020

No. of people on site (approx): 18

Social Media links:

Forecast lorry movements per day (approx): 20

South Ferriby Residents Group

Traffic Movement

  • All Clear 0% 0%
  • Some Lorries 40% 40%
  • Lots of Lorries 0% 0%
  • Temporary Traffic Lights 0% 0%
  • Road Closures 0% 0%

Please drive carefully when you see contractors working close to the side of the road

Outline of work to be undertaken this week

Continue trimming embankment to final profile and commence placing topsoil to West embankment (Adjacent to existing Football pitch)

Continue finishing works on eastern embankment trimming

Continue with new wall construction east of east drain bridge – 1nr joiner fixing base shutters / 2nr steelfixers fixing steel and concrete pours

Continue construction of CEMEX embankment Ch750 to 1125

Useful contact numbers:

Contractor – JBA Bentley – Tom Sherwood – 07870 391 668

Environment Agency – Contact Centre – 03708 506 506

Parish Council           – Cllr Sara Haddon – 07808 958957
– Cllr Roy Holloway – 01652 635 417

Week Beginning: 15th June 2020

No. of people on site (approx): 20

Social Media links:

Forecast lorry movements per day (approx): 20

South Ferriby Residents Group

Traffic Movement

  • All Clear 0% 0%
  • Some Lorries 40% 40%
  • Lots of Lorries 0% 0%
  • Temporary Traffic Lights 40% 40%
  • Road Closures 0% 0%

Please drive carefully when you see contractors working close to the side of the road

Outline of work to be undertaken this week

Continue trimming embankment to final profile and placing topsoil to West embankment (Adjacent to existing Football pitch)

Continue with new wall construction east of east drain bridge – 1nr joiner fixing base shutters / 2nr steelfixers fixing steel and concrete pours

Commence works at East Drain Bridge to raise remove and raise existing parapet wall. Works will involve a lane closure under traffic light control to the eastbound carriageway

Continue construction of CEMEX embankment from Ch50 to 750

Useful contact numbers:

Contractor – JBA Bentley – Tom Sherwood – 07870 391 668

Environment Agency – Contact Centre – 03708 506 506

Parish Council           – Cllr Sara Haddon – 07808 958957
                                   – Cllr Roy Holloway – 01652 635 417

Week Beginning: 22nd June 2020

No. of people on site (approx): 20

Social Media links:

Forecast lorry movements per day (approx): 20

South Ferriby Residents Group

Traffic Movement

  • All Clear 0% 0%
  • Some Lorries 40% 40%
  • Lots of Lorries 0% 0%
  • Temporary Traffic Lights 40% 40%
  • Road Closures 0% 0%

Please drive carefully when you see contractors working close to the side of the road

Outline of work to be undertaken this week

Continue placing topsoil to West embankment (Adjacent to existing Football pitch)

Continue with new wall construction east of east drain bridge – 1nr joiner fixing base shutters / 2nr steelfixers fixing steel and concrete pours

Continue works at East Drain Bridge to raise remove and raise existing parapet wall. Works will involve a lane closure under traffic light control to the eastbound carriageway

Continue construction of CEMEX embankment from Ch50 to 750

Useful contact numbers:

Contractor – JBA Bentley – Tom Sherwood – 07870 391 668

Environment Agency – Contact Centre – 03708 506 506

Parish Council           – Cllr Sara Haddon – 07808 958957
                                  – Cllr Roy Holloway – 01652 635 417

Some parts of South Ferriby are at risk of flooding and with the advent of climate change and a greater focus on environmental issues the Parish Council has prepared a flood contingency plan for those living on lower ground.

Flood Protection Committee

The next Flood Protection Committee meeting will be held on Monday 21st October 2019,at 7.00pm in the Village Hall.
 
Agenda

 

Minutes

FPC Meeting – July 2019

FPC Meeting – April 2019

FPC Meeting – April 2018

FPC Meeting – January 2018

FPC Meeting – November 2017

FPC Meeting – September 2017

FPC meeting – July 2017

FPC meeting – June 2017

Flood Risk Contact List and Important Numbers

For more information about the flood plan contact Sara Haddon or Roy Hollaway via the Clerk on 07393 21 30 30 or by email

 

Emergency Telephone Numbers

South Ferriby Flood Wardens:

Roy Holloway 07899 906433
Dave Mouncey  07799 151255

North Lincolnshire Council  01724 297000
Environment Agency Floodline 0845 988 1188
Anglian Water 08457 919155

Contact the Clerk

Holly Hanson
Appledore
26 Main Street
Horkstow
Barton-upon-Humber
DN18 6BG

T: 07393 21 30 30